Watchdog proposes Beaver County nuke plant
re-licensing delay
By Kim
Leonard TRIBUNE-REVIEW Friday, May 29, 2009
The discovery in April of a small hole in the steel liner of a building
that contains one of the Beaver Valley Power Station's nuclear reactors
has prompted a watchdog group to ask the Nuclear Regulatory Commission to
review safety-test procedures.
Citizen Power, based in Squirrel Hill, petitioned the agency this week
to hold off on relicensing the two nuclear reactors at the plant in
Shippingport while an investigation is conducted. NRC spokesman Neil
Sheehan said Thursday that the request will be reviewed.
Plant owner FirstEnergy Corp. of Akron said some corrosion and a
perforation roughly the size of a paper clip were discovered during
routine checks April 24 while the plant's Unit 1 was taken down for
refueling.
The problem in the layer of steel -- about 3/8 of an inch thick -- was
fixed, and Unit 1 is back in operation, spokesman Todd Schneider said.
Ted Robinson, staff attorney for Citizen Power, said the organization
wants the commission to look at whether requirements for visual checks of
liners and occasional pressure tests are enough to detect leaks in aging
plants such as Beaver Valley -- where corrosion was found and repaired in
2006.
"There are different types of tests they could do," he said.
FirstEnergy is seeking federal approval to run power-generating Units 1
and 2 until 2036 and 2047, respectively. Their original 40-year licenses
run out in 2016 and 2027. An official with the commission is expected to
issue a decision in late September.
"As far as Beaver Valley goes, it's not that we want to stop the
license-renewal process," Robinson said. "We want to make sure the proper
reviews are in place."
Citizen Power's petition contains a statement from Arnold Gundersen, an
adviser with Burlington, Vt.-based Fairewinds Associates, a consulting
firm that deals with nuclear issues. Gundersen contended that differences
in pressure between the outside air and conditions inside Beaver Valley's
reactor might have drawn moisture through the 3-foot-thick concrete
building to voids and wood next to the liner.
Gunderson urged that more testing be done and wrote that "an in-depth
analysis of the corrosion problems that exist between the liner and the
porous concrete may uncover systemic failure mechanisms" that put public
health at risk.
First Energy's Schneider said the interior conditions that Gundersen
cites no longer exist at the plant, but Citizen Power's Robinson said the
corrosion found last month might have been developing for years.
Some blistering paint was the first sign of a problem, Schneider said,
and further inspection and ultrasonic tests found a small perforation.
"It was caused by a piece of wood that had been embedded in the
concrete and was touching the liner," he said.
A section of the liner was cut out and replaced with steel plate and
was tested according to the commission's requirements, he said.
The NRC's Sheehan said an in-house panel will review Citizen Power's
petition and provide a response within 120 days.
FirstEnergy handled the situation properly, Sheehan said. The review of
FirstEnergy's relicensing request, submitted in August 2007, is fairly far
along, and the commission hasn't found any issues so far that would
preclude approval, he said.
|